United States βΊ Grid βΊ Interconnection queues βΊ Iowa
GAS Β· WESTGas project GI-0618, Crawford County
Gas project GI-0618, Crawford County is a 30.0 MW gas request withdrawn in the West interconnection queue, in Crawford County, Iowa, connecting to WAPA/BEPC/HCPD Integrated System.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2006 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GI-0618
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- WAPA/BEPC/HCPD Integrated System
- Connection point (POI)
- Denison
- Location
- Crawford County, Iowa
- Technology
- Gas: 30.0 MW
- Total requested
- 30.0 MW
- Service type
- NRIS and ERIS
- Study phase
- IAP
- Queue status
- Withdrawn
- Entered queue
- 4 December 2006
Location
Marker shows the centre of Crawford County; the queue data does not give exact sites.
Other requests in Crawford County
- Onshore wind project GEN-2017-222, Crawford CountyOnshore wind Β· 180 MW Β· agreement signed
- Onshore wind project GEN-2018-074, Crawford CountyOnshore wind Β· 72.0 MW Β· agreement signed
- Onshore wind project R23, Crawford CountyOnshore wind Β· 100 MW Β· built
- Other project GI-1101, Crawford CountyOther Β· 6.0 MW Β· built
- Onshore wind project GI-0604, Crawford CountyOnshore wind Β· 240 MW Β· withdrawn
- Onshore wind project J896, Crawford CountyOnshore wind Β· 150 MW Β· withdrawn
- Gas project GI-0617, Crawford CountyGas Β· 120 MW Β· withdrawn
- Onshore wind project R29, Crawford CountyOnshore wind Β· 101 MW Β· withdrawn
- Gas project GI-0110, Crawford CountyGas Β· 50.0 MW Β· withdrawn
- Onshore wind project R25, Crawford CountyOnshore wind Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem