🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Louisiana

SOLAR · SPP

Solar project GEN-2016-167, Caddo Parish County

Solar project GEN-2016-167, Caddo Parish County is a 73.5 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Caddo Parish County, Louisiana, connecting to AEP.

Queue statusConsented
  1. PlanningQueued Nov 2016 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingDec 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2016-167
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Lieberman - North Benton 138 kV Line
Location
Caddo Parish County, Louisiana
Technology
Solar: 73.5 MW
Total requested
73.5 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
29 November 2016
Proposed online date
December 2024
Came online
December 2024

Location

Marker shows the centre of Caddo Parish County; the queue data does not give exact sites.

Power plants in Louisiana · Transmission lines in Louisiana

Other requests in Caddo Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem