SOLAR · SPP

Solar project GEN-2017-057, Caddo Parish County

Solar project GEN-2017-057, Caddo Parish County is a 72.5 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Caddo Parish County, Louisiana, connecting to AEP.

Queue statusConsented
  1. PlanningQueued May 2017 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFeb 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2017-057
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Hosston 69kV
Location
Caddo Parish County, Louisiana
Technology
Solar: 72.5 MW
Total requested
72.5 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
30 May 2017
Proposed online date
February 2025
Came online
February 2025

Location

Marker shows the centre of Caddo Parish County; the queue data does not give exact sites.

Power plants in Louisiana · Transmission lines in Louisiana

Other requests in Caddo Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem