SOLAR · SPP

Solar project GEN-2018-050, Caddo Parish County

Solar project GEN-2018-050, Caddo Parish County is a 200 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Caddo Parish County, Louisiana, connecting to AEP.

Queue statusConsented
  1. PlanningQueued May 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2018-050
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Longwood 345kV Substation
Location
Caddo Parish County, Louisiana
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
29 May 2018
Proposed online date
April 2028

Location

Marker shows the centre of Caddo Parish County; the queue data does not give exact sites.

Power plants in Louisiana · Transmission lines in Louisiana

Other requests in Caddo Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem