Onshore wind project GEN-2016-071, Kay County

Onshore wind project GEN-2016-071, Kay County is a 64.6 MW onshore wind request with a signed interconnection agreement in the SPP interconnection queue, in Kay County, Oklahoma, connecting to OGE.

Queue statusConsented
  1. PlanningQueued Mar 2016 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2016-071
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Middleton Tap 138kV Substation
Location
Kay County, Oklahoma
Technology
Wind: 64.6 MW
Total requested
64.6 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
30 March 2016
Proposed online date
February 2028

Location

Marker shows the centre of Kay County; the queue data does not give exact sites.