🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Oklahoma

ONSHORE WIND · SPP

Onshore wind project GEN-2024-GR6, Kay County

Onshore wind project GEN-2024-GR6, Kay County is a 300 MW onshore wind request in interconnection study in the SPP interconnection queue, in Kay County, Oklahoma, connecting to OG&E.

Queue statusIn planning
  1. PlanningQueued Jul 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-GR6
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OG&E
Connection point (POI)
Open Sky 345kV Substation
Location
Kay County, Oklahoma
Technology
Wind: 300 MW
Total requested
300 MW
Service type
Energy only (ERIS)
Study phase
IA PENDING
Queue status
Active
Entered queue
25 July 2024
Proposed online date
May 2027

Location

Marker shows the centre of Kay County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Kay County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem