ONSHORE WIND · SPP

Onshore wind project GEN-2018-013, Dickinson County

Onshore wind project GEN-2018-013, Dickinson County is a 74.1 MW onshore wind request with a signed interconnection agreement in the SPP interconnection queue, in Dickinson County, Kansas, connecting to WERE.

Queue statusConsented
  1. PlanningQueued Apr 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2018-013
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WERE
Connection point (POI)
Abilene Energy Center-Northview 115kV Line
Location
Dickinson County, Kansas
Technology
Wind: 74.1 MW
Total requested
74.1 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
27 April 2018
Proposed online date
December 2026

Location

Marker shows the centre of Dickinson County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Dickinson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem