SOLAR · SPPSolar project GEN-2019-041, Lancaster County
Solar project GEN-2019-041, Lancaster County is a 78.0 MW solar request suspended in the SPP interconnection queue, in Lancaster County, Nebraska, connecting to NPPD.
Queue statusPaused / redesign
- PlanningQueued May 2019 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2019-041
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- NPPD
- Connection point (POI)
- 115kV Monolith Substation
- Location
- Lancaster County, Nebraska
- Technology
- Solar: 78.0 MW
- Total requested
- 78.0 MW
- Service type
- NRIS and ERIS
- Study phase
- IA FULLY EXECUTED/ON SUSPENSION
- Queue status
- Suspended
- Entered queue
- 23 May 2019
- Proposed online date
- December 2028
Location
Marker shows the centre of Lancaster County; the queue data does not give exact sites.
Other requests in Lancaster County
- Onshore wind project GEN-2017-181, Lancaster CountyOnshore wind · 300 MW · agreement signed
- Battery storage project GEN-2021-043, Lancaster CountyBattery storage · 250 MW · agreement signed
- Onshore wind project GEN-2018-125, Lancaster CountyOnshore wind · 231 MW · agreement signed
- Solar project GEN-2021-049, Lancaster CountySolar · 225 MW · agreement signed
- Onshore wind project GEN-2017-182, Lancaster CountyOnshore wind · 128 MW · agreement signed
- Solar project GEN-2021-034, Lancaster CountySolar · 113 MW · agreement signed
- Battery storage project GEN-2021-048, Lancaster CountyBattery storage · 75.0 MW · agreement signed
- Solar project GEN-2013-019, Lancaster CountySolar · 73.6 MW · agreement signed
- Solar project GEN-2013-002, Lancaster CountySolar · 50.6 MW · agreement signed
- Gas project GEN-2024-021, Lancaster CountyGas · 540 MW · in study
- Gas project GEN-2023-224, Lancaster CountyGas · 478 MW · in study
- Gas project GEN-2024-020, Lancaster CountyGas · 390 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem