Solar project GEN-2021-049, Lancaster County

Solar project GEN-2021-049, Lancaster County is a 225 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Lancaster County, Nebraska, connecting to LES.

Queue statusConsented
  1. PlanningQueued Apr 2021 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2029 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2021-049
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
LES
Connection point (POI)
Wagener 115kV Substation
Location
Lancaster County, Nebraska
Technology
Solar: 225 MW
Total requested
225 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
30 April 2021
Proposed online date
September 2029

Location

Marker shows the centre of Lancaster County; the queue data does not give exact sites.

Power plants in Nebraska · Transmission lines in Nebraska

Other requests in Lancaster County