Solar project GEN-2013-019, Lancaster County

Solar project GEN-2013-019, Lancaster County is a 73.6 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Lancaster County, Nebraska, connecting to NPPD.

Queue statusConsented
  1. PlanningQueued Apr 2013 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2013-019
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
NPPD
Connection point (POI)
Monolith 115kV
Location
Lancaster County, Nebraska
Technology
Solar: 73.6 MW
Total requested
73.6 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
17 April 2013
Proposed online date
December 2026

Location

Marker shows the centre of Lancaster County; the queue data does not give exact sites.