🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Nebraska

BATTERY STORAGE · SPP

Battery storage project GEN-2021-048, Lancaster County

Battery storage project GEN-2021-048, Lancaster County is a 75.0 MW battery storage request with a signed interconnection agreement in the SPP interconnection queue, in Lancaster County, Nebraska, connecting to LES.

Queue statusConsented
  1. PlanningQueued Apr 2021 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2029 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2021-048
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
LES
Connection point (POI)
Wagener 115kV Substation
Location
Lancaster County, Nebraska
Technology
Battery: 75.0 MW
Total requested
75.0 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
30 April 2021
Proposed online date
September 2029

Location

Marker shows the centre of Lancaster County; the queue data does not give exact sites.

Power plants in Nebraska · Transmission lines in Nebraska

Other requests in Lancaster County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem