United States › Grid › Interconnection queues › Arkansas
SOLAR · SPPSolar project GEN-2017-231, Franklin County
Solar project GEN-2017-231, Franklin County is a 72.5 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Franklin County, Arkansas, connecting to OGE.
Queue statusConsented
- PlanningQueued Nov 2017 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Mar 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2017-231
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OGE
- Connection point (POI)
- Branch 161kV Substation
- Location
- Franklin County, Arkansas
- Technology
- Solar: 72.5 MW
- Total requested
- 72.5 MW
- Service type
- NRIS and ERIS
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 28 November 2017
- Proposed online date
- March 2027
Location
Marker shows the centre of Franklin County; the queue data does not give exact sites.
Other requests in Franklin County
- Solar project GEN-2021-033, Franklin CountySolar · 204 MW · agreement signed
- Battery storage project GEN-2024-SR2, Franklin CountyBattery storage · 72.5 MW · agreement signed
- Gas project GEN-2024-003, Franklin CountyGas · 102 MW · in study
- Solar project GEN-2024-312, Franklin CountySolar · 50.0 MW · in study
- Battery storage project GEN-2022-049, Franklin CountyBattery storage · 150 MW · withdrawn
- Gas project GEN-2015-019, Franklin CountyGas · 60.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem