United States › Grid › Interconnection queues › Arkansas

SOLAR · SPP

Solar project GEN-2017-231, Franklin County

Solar project GEN-2017-231, Franklin County is a 72.5 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Franklin County, Arkansas, connecting to OGE.

Queue statusConsented
  1. PlanningQueued Nov 2017 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2017-231
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Branch 161kV Substation
Location
Franklin County, Arkansas
Technology
Solar: 72.5 MW
Total requested
72.5 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
28 November 2017
Proposed online date
March 2027

Location

Marker shows the centre of Franklin County; the queue data does not give exact sites.

Power plants in Arkansas · Transmission lines in Arkansas

Other requests in Franklin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem