United States › Grid › Interconnection queues › Arkansas
SOLAR · SPPSolar project GEN-2024-312, Franklin County
Solar project GEN-2024-312, Franklin County is a 50.0 MW solar request in interconnection study in the SPP interconnection queue, in Franklin County, Arkansas, connecting to SWPA.
Queue statusIn planning
- PlanningQueued Mar 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2030 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2024-312
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SWPA
- Connection point (POI)
- Clarksville Ozark 161 kV line
- Location
- Franklin County, Arkansas
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- NRIS and ERIS
- Study phase
- DISIS STAGE
- Queue status
- Active
- Entered queue
- 1 March 2025
- Proposed online date
- December 2030
Location
Marker shows the centre of Franklin County; the queue data does not give exact sites.
Other requests in Franklin County
- Solar project GEN-2021-033, Franklin CountySolar · 204 MW · agreement signed
- Solar project GEN-2017-231, Franklin CountySolar · 72.5 MW · agreement signed
- Battery storage project GEN-2024-SR2, Franklin CountyBattery storage · 72.5 MW · agreement signed
- Gas project GEN-2024-003, Franklin CountyGas · 102 MW · in study
- Battery storage project GEN-2022-049, Franklin CountyBattery storage · 150 MW · withdrawn
- Gas project GEN-2015-019, Franklin CountyGas · 60.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem