ONSHORE WIND · SPP

Onshore wind project GEN-2020-069, Cherry County

Onshore wind project GEN-2020-069, Cherry County is a 52.9 MW onshore wind request in interconnection study in the SPP interconnection queue, in Cherry County, Nebraska, connecting to NPPD.

Queue statusIn planning
  1. PlanningQueued Apr 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingNov 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2020-069
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
NPPD
Connection point (POI)
Cody to Valentine 115kV line
Location
Cherry County, Nebraska
Technology
Wind: 52.9 MW
Total requested
52.9 MW
Service type
NRIS and ERIS
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
24 April 2020
Proposed online date
November 2025
Came online
November 2025

Location

Marker shows the centre of Cherry County; the queue data does not give exact sites.

Power plants in Nebraska · Transmission lines in Nebraska

Other requests in Cherry County