United States › Grid › Interconnection queues › Kansas

SOLAR · SPP

Solar project GEN-2017-022, Wilson County

Solar project GEN-2017-022, Wilson County is a 65.0 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Wilson County, Kansas, connecting to WERE.

Queue statusConsented
  1. PlanningQueued May 2017 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2017-022
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WERE
Connection point (POI)
Altoona- NE Parson 138kV
Location
Wilson County, Kansas
Technology
Solar: 65.0 MW
Total requested
65.0 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
31 May 2017
Proposed online date
March 2027

Location

Marker shows the centre of Wilson County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Wilson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem