SOLAR · SPP

Solar project GEN-2017-230, Lincoln County

Solar project GEN-2017-230, Lincoln County is a 72.5 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Lincoln County, Oklahoma, connecting to OGE.

Queue statusConsented
  1. PlanningQueued Nov 2017 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2017-230
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Tryon 138kV Substation
Location
Lincoln County, Oklahoma
Technology
Solar: 72.5 MW
Total requested
72.5 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
28 November 2017
Proposed online date
May 2027

Location

Marker shows the centre of Lincoln County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Lincoln County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem