Withdrawn queue requests in ISO-NE (New England) — page 10

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown982118.1 GW
Active in queue14.6 GW72 requests
Agreement signed8,609 MW45 requests
Withdrawn982118.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

982 requests · page 10 of 20
ProjectCapacityStatusLocationRegionQueuedOnline
Offshore Wind Increase
Offshore wind
40.0 MWWithdrawn / abandoned MAISO-NE Mar 2019target 2026
Biomass
Other
40.0 MWWithdrawn / abandoned Cheshire, NHISO-NE Nov 2004target 2007
Combined Cycle Upgrade
Gas
40.0 MWWithdrawn / abandoned Providence, RIISO-NE Apr 2016target 2020
Battery Storage
Battery storage
40.0 MWWithdrawn / abandoned Kent, RIISO-NE Oct 2022target 2027
Solar
Solar
40.0 MWWithdrawn / abandoned Hampshire, MAISO-NE Jun 2020target 2023
Wind farm
Onshore wind
39.6 MWWithdrawn / abandoned Oxford, MEISO-NE Aug 2015target 2019
Gas Turbine
Gas
39.0 MWWithdrawn / abandoned Litchfield, CTISO-NE Dec 2006target 2010
(Offshore wind Increase (Q700 +Q1154)
Offshore wind
38.8 MWWithdrawn / abandoned MAISO-NE Feb 2023target 2026
Towantic Energy increase
Gas
38.0 MWWithdrawn / abandoned New Haven, CTISO-NE Dec 2007target 2014
Biomass
Other
37.0 MWWithdrawn / abandoned Windsor, VTISO-NE May 2013target 2015
Palmer Renewable Energy
Other
36.7 MWWithdrawn / abandoned Hampden, MAISO-NE Aug 2008target 2020
Wind Repower
Onshore wind
35.2 MWWithdrawn / abandoned Caledonia, VTISO-NE Dec 2023target 2026
E. Winchendon Substation - NG WMA Group 3
Solar + storage
35.0 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2026
Gas Turbine
Gas
35.0 MWWithdrawn / abandoned Penobscot, MEISO-NE Oct 2008target 2014
Solar
Solar
35.0 MWWithdrawn / abandoned Oxford, MEISO-NE Aug 2019target 2024
Gas Turbine Capacity Increase ( See queue position
Gas
35.0 MWWithdrawn / abandoned Fairfield, CTISO-NE Dec 2007target 2010
Solar
Solar
35.0 MWWithdrawn / abandoned Merrimack, NHISO-NE Nov 2019target 2022
Wind Project
Onshore wind
34.9 MWWithdrawn / abandoned Penobscot, MEISO-NE Jul 2007target 2012
Repowering Increase
Gas
34.8 MWWithdrawn / abandoned Norfolk, MAISO-NE Apr 2017target 2021
Wood River - NG WRI DG Area Study #2 >5 MW
Solar
34.4 MWWithdrawn / abandoned Washington, RIISO-NE Aug 2020target 2025
Wind Project
Onshore wind
34.0 MWWithdrawn / abandoned Coos, NHISO-NE Feb 2007target 2014
Wind
Onshore wind
34.0 MWWithdrawn / abandoned Orleans, VTISO-NE Jun 2008target 2011
Eversource Group @ Tremont Substation 713
Solar + storage
33.7 MWWithdrawn / abandoned Plymouth, MAISO-NE Apr 2020target 2023
Solar
Solar
33.1 MWWithdrawn / abandoned Grafton, NHISO-NE Jul 2019target 2022
Combined Cycle Increase
Gas
33.0 MWWithdrawn / abandoned Rockingham, NHISO-NE Oct 2014target 2015
Wind
Onshore wind
33.0 MWWithdrawn / abandoned Hillsborough, NHISO-NE Aug 2011target 2015
Fair Haven Biomass
Other
33.0 MWWithdrawn / abandoned Rutland, VTISO-NE May 2010target 2016
Kibby Wind Expansion
Onshore wind
33.0 MWWithdrawn / abandoned Franklin, MEISO-NE Sep 2009target 2014
Wind
Onshore wind
33.0 MWWithdrawn / abandoned Franklin, MEISO-NE May 2013target 2016
Biomass
Other
33.0 MWWithdrawn / abandoned Bennington, VTISO-NE Jun 2010target 2013
Solar
Solar
31.4 MWWithdrawn / abandoned Knox, MEISO-NE Feb 2021target 2024
Biomass
Other
30.0 MWWithdrawn / abandoned Windsor, VTISO-NE Feb 2009target 2011
Fuel Cell
Gas
30.0 MWWithdrawn / abandoned Fairfield, CTISO-NE Jun 2006target 2008
Solar
Solar
30.0 MWWithdrawn / abandoned Cheshire, NHISO-NE Mar 2017target 2018
Solar
Solar
30.0 MWWithdrawn / abandoned Cheshire, NHISO-NE Apr 2018target 2024
Combined Cycle Uprate
Gas
30.0 MWWithdrawn / abandoned Penobscot, MEISO-NE Feb 2015target 2018
Biomass
Other
30.0 MWWithdrawn / abandoned Windsor, VTISO-NE Sep 2008target 2011
Deerfield Wind
Onshore wind
30.0 MWWithdrawn / abandoned Bennington, VTISO-NE Sep 2008target 2013
Combined Cycle Upgrate #3
Gas
30.0 MWWithdrawn / abandoned Worcester, MAISO-NE Feb 2015target 2018
Solar
Solar
30.0 MWWithdrawn / abandoned Washington, RIISO-NE Aug 2018target 2020
Wind
Onshore wind
30.0 MWWithdrawn / abandoned Hampden, MAISO-NE May 2010target 2012
GMP Generator Replacement
Gas
29.5 MWWithdrawn / abandoned Chittenden, VTISO-NE Aug 2008target 2014
Eversource Group @ Industrial Park 636
Solar + storage
29.1 MWWithdrawn / abandoned Bristol, MAISO-NE Apr 2020target 2023
Gas Turbine (Additional Capacity)
Other
29.0 MWWithdrawn / abandoned Suffolk, MAISO-NE May 2006target 2008
Power Station Increase
Nuclear
29.0 MWWithdrawn / abandoned New London, CTISO-NE Dec 2009target 2011
Fuel Cell
Gas
28.9 MWWithdrawn / abandoned Fairfield, CTISO-NE Dec 2006target 2009
EE Group @ Blandford
Solar + storage
28.9 MWWithdrawn / abandoned Hampshire, MAISO-NE Jun 2023target 2024
Wind
Onshore wind
28.8 MWWithdrawn / abandoned Washington, RIISO-NE Aug 2009target 2012
CMP Lakewood 115 kV SS - Winslow-Lakewood Areas Study
Solar
28.7 MWWithdrawn / abandoned Somerset, MEISO-NE Feb 2021target 2024
Hydro
Hydro
28.3 MWWithdrawn / abandoned Oxford, MEISO-NE Feb 2016target 2019
Page 10 of 20

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)