HYDRO Β· ISO-NE

Hydro

Hydro is a 28.3 MW hydro request withdrawn in the ISO-NE interconnection queue, in Oxford County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2016 (completed)
  2. Withdrawn / abandonedApr 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
597
Grid region
ISO-NE (New England)
Connection point (POI)
CMP Section 230 (115 kV) at southeast end, high side of Verso Androscoggin substation
Location
Oxford County, Maine
Technology
Hydro: 28.3 MW
Total requested
28.3 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
24 February 2016
Proposed online date
June 2019
Withdrawn
April 2018

Location

Marker shows the centre of Oxford County; the queue data does not give exact sites.

Power plants in Maine Β· Transmission lines in Maine

Other requests in Oxford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem