United States βΊ Grid βΊ Interconnection queues βΊ Maine
ONSHORE WIND Β· ISO-NERoxWind
RoxWind is a 15.3 MW onshore wind request built and operating in the ISO-NE interconnection queue, in Oxford County, Maine.
Request details
- Queue ID
- 655
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- 34.5 kV Bus at Roxbury Substation, Roxbury, Maine
- Location
- Oxford County, Maine
- Technology
- Wind: 15.3 MW
- Total requested
- 15.3 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed
- Queue status
- Operational
- Entered queue
- 15 June 2017
- Agreement signed
- 11 May 2020
- Proposed online date
- November 2021
Location
Marker shows the centre of Oxford County; the queue data does not give exact sites.
Other requests in Oxford County
- Twin Energy WindOnshore wind Β· 18.3 MW Β· agreement signed
- Roxbury SolarSolar Β· 2.0 MW Β· agreement signed
- Record Hill WindOnshore wind Β· 50.6 MW Β· built
- Canton Mountain WindsOnshore wind Β· 19.3 MW Β· built
- Spruce Mountain WindOnshore wind Β· 18.0 MW Β· built
- Rumford Uprate and Battery additionOther Β· 8.5 MW Β· built
- SolarSolar Β· 4.6 MW Β· built
- SolarSolar Β· 4.6 MW Β· built
- Spruce Mountain Wind IncreaseOnshore wind Β· 2.0 MW Β· built
- 13665 Felt Road SolarSolar + storage Β· 2.0 MW Β· built
- Rumford Falls Unit #3 increaseHydro Β· 1.3 MW Β· built
- Rumford Power Repair for Performance UpgradeGas Β· 0.2 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem