ONSHORE WIND · ISO-NE

Spruce Mountain Wind Increase

Spruce Mountain Wind Increase is a 2.0 MW onshore wind request built and operating in the ISO-NE interconnection queue, in Oxford County, Maine.

Queue statusOperating
  1. PlanningQueued Jan 2010 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2010 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
323
Grid region
ISO-NE (New England)
Connection point (POI)
CMP Woodstock substation
Location
Oxford County, Maine
Technology
Wind: 2.0 MW
Total requested
2.0 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
21 January 2010
Proposed online date
December 2010
Withdrawn
July 2010

Location

Marker shows the centre of Oxford County; the queue data does not give exact sites.

Power plants in Maine · Transmission lines in Maine

Other requests in Oxford County