Palmer Renewable Energy

Palmer Renewable Energy is a 36.7 MW other request withdrawn in the ISO-NE interconnection queue, in Hampden County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2008 (completed)
  2. Withdrawn / abandonedOct 2019 (project stopped here)
  3. ConsentedDec 2017 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
273
Grid region
ISO-NE (New England)
Connection point (POI)
115 kV line near E. Springfield substation
Location
Hampden County, Massachusetts
Technology
Other: 36.7 MW
Total requested
36.7 MW
Service type
Energy only (ERIS)
Study phase
Executed
Queue status
Withdrawn
Entered queue
3 August 2008
Agreement signed
13 December 2017
Proposed online date
July 2020
Withdrawn
October 2019

Location

Marker shows the centre of Hampden County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Hampden County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem