United States › Grid › Interconnection queues › New Hampshire

GAS · ISO-NE

Combined Cycle Increase

Combined Cycle Increase is a 33.0 MW gas request withdrawn in the ISO-NE interconnection queue, in Rockingham County, New Hampshire.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2014 (completed)
  2. Withdrawn / abandonedNov 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
479
Grid region
ISO-NE (New England)
Connection point (POI)
Watts Brook, North Litchfield
Location
Rockingham County, New Hampshire
Technology
Gas: 33.0 MW
Total requested
33.0 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
17 October 2014
Proposed online date
March 2015
Withdrawn
November 2014

Location

Marker shows the centre of Rockingham County; the queue data does not give exact sites.