United States › Grid › Interconnection queues › New Hampshire

GAS · ISO-NE

Combined Cycle Capacity Increase/ Generator Change

Combined Cycle Capacity Increase/ Generator Change is a 904 MW gas request withdrawn in the ISO-NE interconnection queue, in Rockingham County, New Hampshire.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2007 (completed)
  2. Withdrawn / abandonedJul 2009 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
226
Grid region
ISO-NE (New England)
Connection point (POI)
345 kV Seabrook Substation
Location
Rockingham County, New Hampshire
Technology
Gas: 904 MW
Total requested
904 MW
Service type
Other
Queue status
Withdrawn
Entered queue
5 September 2007
Proposed online date
June 2013
Withdrawn
July 2009

Location

Marker shows the centre of Rockingham County; the queue data does not give exact sites.

Power plants in New Hampshire · Transmission lines in New Hampshire

Other requests in Rockingham County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem