SOLAR Β· ISO-NE

Solar

Solar is a 10.0 MW solar request withdrawn in the ISO-NE interconnection queue, in Rockingham County, New Hampshire.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2018 (completed)
  2. Withdrawn / abandonedJul 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
770
Grid region
ISO-NE (New England)
Connection point (POI)
Eversource 34.5 kV feeder (3184 circuit), Mammoth Rd substation
Location
Rockingham County, New Hampshire
Technology
Solar: 10.0 MW
Total requested
10.0 MW
Queue status
Withdrawn
Entered queue
20 June 2018
Proposed online date
June 2019
Withdrawn
July 2018

Location

Marker shows the centre of Rockingham County; the queue data does not give exact sites.

Power plants in New Hampshire Β· Transmission lines in New Hampshire

Other requests in Rockingham County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem