United States › Grid › Interconnection queues › Rhode Island

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 40.0 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Kent County, Rhode Island.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2022 (completed)
  2. Withdrawn / abandonedOct 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1326
Grid region
ISO-NE (New England)
Connection point (POI)
Line tap on the S-171 South 115 kV transmission line, roughly 4 miles from West Cranston Substation and 1.5 miles from Drumrock Substation.
Location
Kent County, Rhode Island
Technology
Battery: 40.0 MW
Total requested
40.0 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
19 October 2022
Proposed online date
December 2027
Withdrawn
October 2023

Location

Marker shows the centre of Kent County; the queue data does not give exact sites.

Power plants in Rhode Island · Transmission lines in Rhode Island

Other requests in Kent County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem