United States › Grid › Interconnection queues › Rhode Island

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 62.8 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Kent County, Rhode Island.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2022 (completed)
  2. Withdrawn / abandonedOct 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1240
Grid region
ISO-NE (New England)
Connection point (POI)
National Grid Kent County Substation - 115kV open line position between 4T3T and 3T10 breakers.
Location
Kent County, Rhode Island
Technology
Battery: 62.8 MW
Total requested
62.8 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
25 March 2022
Proposed online date
December 2025
Withdrawn
October 2024

Location

Marker shows the centre of Kent County; the queue data does not give exact sites.

Power plants in Rhode Island · Transmission lines in Rhode Island

Other requests in Kent County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem