🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Rhode Island

SOLAR · ISO-NE

Warren Substation – NG RI-Warren-20-Comp-1 Study

Warren Substation – NG RI-Warren-20-Comp-1 Study is a 6.9 MW solar request withdrawn in the ISO-NE interconnection queue, in Kent County, Rhode Island, connecting to NGRID.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2020 (completed)
  2. Withdrawn / abandonedJun 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1039
Grid region
ISO-NE (New England)
Utility / transmission owner
NGRID
Connection point (POI)
NG feeder 5F2, Warren Substation
Location
Kent County, Rhode Island
Technology
Solar: 6.9 MW
Total requested
6.9 MW
Queue status
Withdrawn
Entered queue
19 August 2020
Proposed online date
August 2024
Withdrawn
June 2025

Location

Marker shows the centre of Kent County; the queue data does not give exact sites.

Power plants in Rhode Island · Transmission lines in Rhode Island

Other requests in Kent County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem