ONSHORE WIND Β· ISO-NE

Wind

Wind is a 30.0 MW onshore wind request withdrawn in the ISO-NE interconnection queue, in Hampden County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2010 (completed)
  2. Withdrawn / abandonedMar 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
334
Grid region
ISO-NE (New England)
Connection point (POI)
Section #175 115kV line from Palmer to Little Rest
Location
Hampden County, Massachusetts
Technology
Wind: 30.0 MW
Total requested
30.0 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
14 May 2010
Proposed online date
December 2012
Withdrawn
March 2011

Location

Marker shows the centre of Hampden County; the queue data does not give exact sites.

Power plants in Massachusetts Β· Transmission lines in Massachusetts

Other requests in Hampden County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem