πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Hampshire

ONSHORE WIND Β· ISO-NE

Wind Project

Wind Project is a 34.0 MW onshore wind request withdrawn in the ISO-NE interconnection queue, in Coos County, New Hampshire.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2007 (completed)
  2. Withdrawn / abandonedAug 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
200
Grid region
ISO-NE (New England)
Connection point (POI)
New Hampshire Electric Coop 34.5 kV line
Location
Coos County, New Hampshire
Technology
Wind: 34.0 MW
Total requested
34.0 MW
Queue status
Withdrawn
Entered queue
21 February 2007
Proposed online date
November 2014
Withdrawn
August 2013

Location

Marker shows the centre of Coos County; the queue data does not give exact sites.

Power plants in New Hampshire Β· Transmission lines in New Hampshire

Other requests in Coos County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem