OTHER · ISO-NEBerlin Energy Uprate and Battery Addition
Berlin Energy Uprate and Battery Addition is a 15.0 MW other request built and operating in the ISO-NE interconnection queue, in Coos County, New Hampshire.
Request details
- Queue ID
- 1103
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- 22kV bus at Brookfield owned Goebel St Substation connected to the Eversource Berlin 115kV substation.
- Location
- Coos County, New Hampshire
- Technology
- Hydro: 15.0 MW · Battery
- Total requested
- 15.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed
- Queue status
- Operational
- Entered queue
- 10 March 2021
- Agreement signed
- 14 September 2023
- Proposed online date
- November 2023
Location
Marker shows the centre of Coos County; the queue data does not give exact sites.
Power plants in New Hampshire · Transmission lines in New Hampshire
Other requests in Coos County
- Granite Reliable PowerOnshore wind · 94.5 MW · built
- Burgess BioPowerOther · 58.7 MW · built
- GLHA James River/Fraser Paper7Hydro · 25.0 MW · built
- Burgess BioPower IncreaseOther · 9.0 MW · built
- Jericho WindOnshore wind · 8.6 MW · built
- Jericho Wind expansionOnshore wind · 3.5 MW · built
- WindOnshore wind · 180 MW · withdrawn
- WindOnshore wind · 146 MW · withdrawn
- Solar + Battery StorageSolar + storage · 113 MW · withdrawn
- Biomass ProjectOther · 67.5 MW · withdrawn
- SolarSolar · 60.0 MW · withdrawn
- SolarSolar · 60.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem