United States › Grid › Interconnection queues › New Hampshire

SOLAR + STORAGE · ISO-NE

Solar + Battery Storage

Solar + Battery Storage is a 113 MW solar + storage request withdrawn in the ISO-NE interconnection queue, in Coos County, New Hampshire.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2021 (completed)
  2. Withdrawn / abandonedFeb 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1135
Grid region
ISO-NE (New England)
Connection point (POI)
Eversource W179-1 115 kV Line between Berlin and Pontook Hydro Substations, 11.5 miles from the Berlin Substation
Location
Coos County, New Hampshire
Technology
Solar: 113 MW · Battery
Total requested
113 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
13 May 2021
Proposed online date
May 2025
Withdrawn
February 2023

Location

Marker shows the centre of Coos County; the queue data does not give exact sites.

Power plants in New Hampshire · Transmission lines in New Hampshire

Other requests in Coos County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem