GAS · ISO-NE

Gas Turbine Capacity Increase ( See queue position

Gas Turbine Capacity Increase ( See queue position is a 35.0 MW gas request withdrawn in the ISO-NE interconnection queue, in Fairfield County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2007 (completed)
  2. Withdrawn / abandonedOct 2008 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
239
Grid region
ISO-NE (New England)
Connection point (POI)
UI 345 kV Singer Substation
Location
Fairfield County, Connecticut
Technology
Gas: 35.0 MW · Oil
Total requested
35.0 MW
Service type
Other
Queue status
Withdrawn
Entered queue
12 December 2007
Proposed online date
September 2010
Withdrawn
October 2008

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in Fairfield County