Grid connection projects in the connection queue

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown21958.4 GW in total
In planning1,590scoping or awaiting consent
Consented or building265closest to connecting
Built400connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

219 projects · page 3 of 5
ProjectCapacityStageConnection siteFrom
Kennoxhead Wind Farm
Onshore wind · Perigus Energy UK Limited
112 MWConsents Approved Coalburn 132kV
SP Transmission (south Scotland)
Apr 2028
Beaw Field Wind Farm
Onshore wind · Beaw Field Shetland Limited
102 MWConsents Approved Beaw Field 132/33kV Substation
SSEN Transmission (north Scotland)
Oct 2032
Bradford West 100MW
Battery storage · Old Allen Road BESS Limited
100 MWConsents Approved Bradford West 275kV Substation
National Grid (England & Wales)
May 2027
Flemyland Battery Storage
Battery storage · Flemyland Battery Storage Limited
100 MWConsents Approved Kilwinning 132/33kV
SP Transmission (south Scotland)
Apr 2029
Pentland Floating Offshore Wind Farm
Offshore wind · Highland Wind Limited
100 MWConsents Approved Pentland Floating Offshore Wind Farm 132/66kV substation
SSEN Transmission (north Scotland)
Apr 2028
Walpole 2 (tertiary)
Solar + storage · Enso Green Holdings R Limited
100 MWConsents Approved Walpole 132kV Substation
National Grid (England & Wales)
Oct 2027
Barking BESS
Battery storage · O&G Solar (SPV 52) Limited
100 MWConsents Approved Barking West GSP
National Grid (England & Wales)
Oct 2028
Ferrybridge B BESS & Solar Substation
Solar + storage · O&G Solar (SPV 19) Limited
100 MWConsents Approved Ferrybridge B 132kV Substation
National Grid (England & Wales)
Oct 2035
Shaftesbury Energy Park
Battery storage · Tagenergy Development UK Limited
100 MWConsents Approved Shaftesbury 132kV Substation
National Grid (England & Wales)
Dec 2036
Chleansaid Wind Farm
Onshore wind · Esb Asset Development UK Limited
96 MWConsents Approved Chleansaid Wind Farm 132kV Substation
SSEN Transmission (north Scotland)
Sep 2028
Chirmorie Wind Farm
Onshore wind · Chirmorie Wind Farm Limited
91 MWConsents Approved Chirmorie Wind Farm substation
SP Transmission (south Scotland)
Apr 2027
Greenburn Mixed Technology
Onshore wind · Reg Greenburn Limited
90 MWConsents Approved Greenburn Mixed Technology 132kV Substation
SP Transmission (south Scotland)
Jun 2028
Royle Farm BESS
Battery storage · Aludra BESS Ltd
90 MWConsents Approved Drakelow 132kV Substation
National Grid (England & Wales)
Oct 2028
Windy Standard III Wind Farm
Onshore wind · Windy Standard III Limited
88 MWConsents Approved Dun Hill 132/33kV
SP Transmission (south Scotland)
Oct 2027
Artfield Forest Wind Farm
Onshore wind · Artfield Forest Wind Farm Ltd
86 MWConsents Approved Artfield Forest Wind Farm 132kV Substation
SP Transmission (south Scotland)
Jun 2030
Lethans Wind Farm Extension
Onshore wind · Lethans East Wind Farm Limited
85 MWConsents Approved Lethans Collector 132kV Substation
SP Transmission (south Scotland)
Oct 2029
Shepherds Rig Wind Farm
Onshore wind · Sett Wind Development Limited
85 MWConsents Approved Shepards Rig 132/33kV
SP Transmission (south Scotland)
May 2030
Shbec
Other · Ttep Shb Ltd
83 MWConsents Approved South Humber Bank 400kV Substation
National Grid (England & Wales)
Jul 2029
Stella Battery Energy Storage
Battery storage · Capella BESS Ltd
78 MWConsents Approved Stella South GSP
National Grid (England & Wales)
Nov 2026
Blarghour Wind
Onshore wind · Blarghour Wind Farm Limited
67 MWConsents Approved Blarghour Substation
SSEN Transmission (north Scotland)
Apr 2029
Cairn Duhie Wind Farm
Onshore wind · Cairn Duhie Energy Limited
67 MWConsents Approved Berryburn 275/33kV GSP Substation
SSEN Transmission (north Scotland)
Oct 2028
Strathy Wood Wind Farm
Onshore wind · RWE Renewables UK Onshore Wind Limited
64 MWConsents Approved Strathy Wood 132/33kV Substation
SSEN Transmission (north Scotland)
Dec 2029
Benthead Solar
Solar + storage · Benthead Solar Limited
63 MWConsents Approved Kilwinning 132/33kV
SP Transmission (south Scotland)
Apr 2025
Dolphingstone Farm
Battery storage · Bssl East Lothian 1 Ltd
63 MWConsents Approved Cockenzie 275/33kV Substation
SP Transmission (south Scotland)
Oct 2028
Tomchrasky Wind Farm
Onshore wind · E Power Limited
63 MWConsents Approved Tomchrasky Wind Farm 132/33kV Substation
SSEN Transmission (north Scotland)
Mar 2032
Inchbean Energy Park
Battery storage · Brockwell Storage & Solar Limited
60 MWConsents Approved Kilmarnock Town 275/33kV Substation
SP Transmission (south Scotland)
Feb 2027
Bicker Fen 1 Solar
Solar + storage · Agr Solar 2 Limited
57 MWConsents Approved Bicker Fen 400kV Substation
National Grid (England & Wales)
Apr 2033
Berkswell (Tertiary)
Solar + storage · Enso Green Holdings P Limited
57 MWConsents Approved Berkswell 275kV Substation
National Grid (England & Wales)
May 2028
Braintree
Solar + storage · Pivoted Power LLP
57 MWConsents Approved Braintree 400kV Substation
National Grid (England & Wales)
May 2027
Bramford Tertiary
Solar + storage · Bramford Green Limited
57 MWConsents Approved Bramford 400kV Substation
National Grid (England & Wales)
Oct 2029
Enderby Tertiary
Solar · Clump Farm Solar Limited
57 MWConsents Approved Enderby 400kV Substation
National Grid (England & Wales)
Aug 2028
Fferm Solar Pentir
Battery storage · Lightsource Spv 191 Limited
57 MWConsents Approved Pentir 400kV Substation
National Grid (England & Wales)
Oct 2028
High Marnham (Tertiary)
Solar + storage · Enso Green Holdings K Limited
57 MWConsents Approved High Marnham 400kV Substation
National Grid (England & Wales)
Oct 2030
Kirkby
Battery storage · Kirkby Battery Storage Ltd
57 MWConsents Approved Kirkby 275/33kV Substation
National Grid (England & Wales)
Oct 2037
Legacy Tertiary Connection
Battery storage · Hd639Leg Limited
57 MWConsents Approved Legacy 400kV Substation
National Grid (England & Wales)
Aug 2024
Lister Battery (formerly Lister Drive)
Battery storage · Lister Battery Ltd
57 MWConsents Approved Lister Drive 275kV Substation
National Grid (England & Wales)
Sep 2029
Mill Hill Tertiary Connection
Battery storage · HB333MIL LTD
57 MWConsents Approved Mill Hill 275kV Substation
National Grid (England & Wales)
Oct 2025
Monets Garden
Battery storage · Monets Garden Battery Ltd
57 MWConsents Approved Osbaldwick 400kV Substation
National Grid (England & Wales)
Jun 2027
Norwich
Solar + storage · Pivoted Power LLP
57 MWConsents Approved Norwich Main 400kV Substation
National Grid (England & Wales)
Dec 2025
Penwortham BESS
Battery storage · Penwortham (Bes) Ltd
57 MWConsents Approved Penwortham 400kV Substation
National Grid (England & Wales)
Oct 2028
Rayleigh 1 Tertiary
Solar + storage · Rayleigh Green Limited
57 MWConsents Approved Rayleigh Main 400kV Substation
National Grid (England & Wales)
Oct 2028
Rochdale BESS
Battery storage · Rochdale (BES) Ltd
57 MWConsents Approved Rochdale 275kV Substation
National Grid (England & Wales)
Oct 2029
Thorpe Marsh 1 (Tertiary)
Solar + storage · Enso Green Holdings I Limited
57 MWConsents Approved Thorpe Marsh 400kV Substation
National Grid (England & Wales)
Oct 2028
Warley
Battery storage · Warley Battery Storage Limited
57 MWConsents Approved Warley 275kV Substation
National Grid (England & Wales)
Oct 2028
West Weybridge
Battery storage · El (West Weybridge) Limited
57 MWConsents Approved West Weybridge 275kV Substation
National Grid (England & Wales)
Sep 2028
Wymondley
Solar + storage · Priory Generation Limited
57 MWConsents Approved Wymondley 400kV Substation
National Grid (England & Wales)
May 2027
Coylton 275kV Greener Grid Park
Battery storage · Coylton Energy Limited
50 MWConsents Approved Coylton 275kV substation
SP Transmission (south Scotland)
May 2026
High Constellation Windfarm
Onshore wind · High Constellation Windfarm Limited
50 MWConsents Approved High Constellation 132/33kV Substation
SSEN Transmission (north Scotland)
Oct 2028
Lairg II Wind Farm
Onshore wind · Lairg II LLP
50 MWConsents Approved Lairg GSP
SSEN Transmission (north Scotland)
Jul 2027
Overhill Wind Farm
Onshore wind · Energyfarm UK Overhill LLP
50 MWConsents Approved Overhill 132kV Substation
SP Transmission (south Scotland)
Jun 2029

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.