Grid infrastructure βΊ Connection queue βΊ Solar
SOLAR Β· NGETEnderby Tertiary
Enderby Tertiary is a 57 MW solar project consented, connecting to the National Grid (England & Wales) network at Enderby 400kV Substation, with capacity due from August 2028. The connection agreement is held by Clump Farm Solar Limited.
Project stageConsented
- Planning (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingFrom Aug 2028 (not yet reached)
- Closed (not yet reached)
Connection details
- NESO project number
- PRO-000430
- Customer
- Clump Farm Solar Limited
- Technology
- PV Array (Photo Voltaic/solar)
- Total capacity
- 57 MW
- Change in this agreement
- +57 MW
- Capacity effective from
- 31 August 2028
- Connection site
- Enderby 400kV Substation
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Consents Approved
- Connections reform gate
- Gate 2
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Enderby 400kV Substation