Walpole 2 (tertiary)

Walpole 2 (tertiary) is a 100 MW solar + storage project consented, connecting to the National Grid (England & Wales) network at Walpole 132kV Substation, with capacity due from October 2027. The connection agreement is held by Enso Green Holdings R Limited.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2027 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-000505
Customer
Enso Green Holdings R Limited
Technology
Energy Storage System, PV Array (Photo Voltaic/solar)
Total capacity
100 MW
Change in this agreement
+100 MW
Capacity effective from
31 October 2027
Connection site
Walpole 132kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Consents Approved

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Walpole Β· Grid map

Other projects at Walpole 132kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem