Grid infrastructure βΊ Connection queue βΊ Solar + storage
SOLAR + STORAGE Β· NGETNorwich
Norwich is a 57 MW solar + storage project consented, connecting to the National Grid (England & Wales) network at Norwich Main 400kV Substation, with capacity due from December 2025. The connection agreement is held by Pivoted Power LLP.
Project stageConsented
- Planning (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingFrom Dec 2025 (not yet reached)
- Closed (not yet reached)
Connection details
- NESO project number
- PRO-001077
- Customer
- Pivoted Power LLP
- Technology
- Energy Storage System, PV Array (Photo Voltaic/solar)
- Total capacity
- 57 MW
- Change in this agreement
- +57 MW
- Capacity effective from
- 18 December 2025
- Connection site
- Norwich Main 400kV Substation
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Consents Approved
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Norwich Main 400kV Substation
- Hornsea Power Station 3Offshore wind Β· 3.0 GW Β· Consents Approved
- Hornsea Power Station 3Offshore wind Β· 2.3 GW Β· Consents Approved
- Scira-Dudgeon ExtensionOffshore wind Β· 1.4 GW Β· Scoping
- Scira-Dudgeon ExtensionOffshore wind Β· 950 MW Β· Scoping
- Scira-Dudgeon ExtensionOffshore wind Β· 719 MW Β· Scoping
- Norwich 2Solar Β· 28 MW Β· Scoping
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem