Inchbean Energy Park

Inchbean Energy Park is a 60 MW battery storage project consented, connecting to the SP Transmission (south Scotland) network at Kilmarnock Town 275/33kV Substation, with capacity due from February 2027. The connection agreement is held by Brockwell Storage & Solar Limited.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom Feb 2027 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-002453
Customer
Brockwell Storage & Solar Limited
Technology
Energy Storage System
Total capacity
60 MW
Change in this agreement
+60 MW
Capacity effective from
8 February 2027
Connection site
Kilmarnock Town 275/33kV Substation
Transmission owner
SP Transmission (south Scotland)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Consents Approved
Connections reform gate
Gate 2

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Kilmarnock Town · Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem