Grid infrastructure βΊ Connection queue βΊ Solar + storage
SOLAR + STORAGE Β· NGETBicker Fen 1 Solar
Bicker Fen 1 Solar is a 57 MW solar + storage project consented, connecting to the National Grid (England & Wales) network at Bicker Fen 400kV Substation, with capacity due from April 2033. The connection agreement is held by Agr Solar 2 Limited.
Project stageConsented
- Planning (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingFrom Apr 2033 (not yet reached)
- Closed (not yet reached)
Connection details
- NESO project number
- PRO-001034-2
- Customer
- Agr Solar 2 Limited
- Technology
- Energy Storage System, PV Array (Photo Voltaic/solar)
- Total capacity
- 57 MW
- Change in this agreement
- +7.1 MW
- Capacity effective from
- 1 April 2033
- Connection site
- Bicker Fen 400kV Substation
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Consents Approved
- Connections reform gate
- Gate 2
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Bicker Fen 400kV Substation
- Viking Link Denmark InterconnectorInterconnector Β· 1.5 GW Β· Built
- Bicker Fenn Energy ParkSolar + storage Β· 600 MW Β· Scoping
- Heckington Fen Solar ParkSolar + storage Β· 400 MW Β· Scoping
- Bicker Fen 2 SolarSolar + storage Β· 57 MW Β· Scoping
- Bicker Fen 2 SolarSolar + storage Β· 50 MW Β· Awaiting Consents
- Bicker Fen 1 SolarSolar + storage Β· 50 MW Β· Under Construction/Commissioning
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem