Bradford West 100MW

Bradford West 100MW is a 100 MW battery storage project consented, connecting to the National Grid (England & Wales) network at Bradford West 275kV Substation, with capacity due from May 2027. The connection agreement is held by Old Allen Road BESS Limited.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom May 2027 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-001874
Customer
Old Allen Road BESS Limited
Technology
Energy Storage System
Total capacity
100 MW
Change in this agreement
+100 MW
Capacity effective from
31 May 2027
Connection site
Bradford West 275kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Consents Approved

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Bradford West · Grid map

Other projects at Bradford West 275kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem