Grid infrastructure βΊ Connection queue βΊ Onshore wind
ONSHORE WIND Β· SPTKennoxhead Wind Farm
Kennoxhead Wind Farm is a 112 MW onshore wind project consented, connecting to the SP Transmission (south Scotland) network at Coalburn 132kV, with capacity due from April 2028. The connection agreement is held by Perigus Energy UK Limited.
Project stageConsented
- Planning (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingFrom Apr 2028 (not yet reached)
- Closed (not yet reached)
Connection details
- NESO project number
- PRO-000319
- Customer
- Perigus Energy UK Limited
- Technology
- Wind Onshore
- Total capacity
- 112 MW
- Change in this agreement
- +112 MW
- Capacity effective from
- 28 April 2028
- Connection site
- Coalburn 132kV
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Consents Approved
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem