🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

Grid infrastructure › Connection queue › Battery storage

BATTERY STORAGE · NGET

Lister Battery (formerly Lister Drive)

Lister Battery (formerly Lister Drive) is a 57 MW battery storage project consented, connecting to the National Grid (England & Wales) network at Lister Drive 275kV Substation, with capacity due from September 2029. The connection agreement is held by Lister Battery Ltd.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom Sep 2029 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-001088
Customer
Lister Battery Ltd
Technology
Energy Storage System
Total capacity
57 MW
Change in this agreement
+57 MW
Capacity effective from
30 September 2029
Connection site
Lister Drive 275kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Consents Approved
Connections reform gate
Gate 2

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Lister Drive · Grid map

Other projects at Lister Drive 275kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem