Grid infrastructure › Connection queue › Solar + storage

SOLAR + STORAGE · NGET

Ferrybridge B BESS & Solar Substation

Ferrybridge B BESS & Solar Substation is a 100 MW solar + storage project consented, connecting to the National Grid (England & Wales) network at Ferrybridge B 132kV Substation, with capacity due from October 2035. The connection agreement is held by O&G Solar (SPV 19) Limited.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2035 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-002521
Customer
O&G Solar (SPV 19) Limited
Technology
Energy Storage System, PV Array (Photo Voltaic/solar)
Total capacity
100 MW
Change in this agreement
+100 MW
Capacity effective from
24 October 2035
Connection site
Ferrybridge B 132kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Consents Approved

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Ferrybridge B · Grid map

Other projects at Ferrybridge B 132kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem