Grid infrastructure βΊ Connection queue βΊ Battery storage
BATTERY STORAGE Β· SPTFlemyland Battery Storage
Flemyland Battery Storage is a 100 MW battery storage project consented, connecting to the SP Transmission (south Scotland) network at Kilwinning 132/33kV, with capacity due from April 2029. The connection agreement is held by Flemyland Battery Storage Limited.
Project stageConsented
- Planning (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingFrom Apr 2029 (not yet reached)
- Closed (not yet reached)
Connection details
- NESO project number
- PRO-002360
- Customer
- Flemyland Battery Storage Limited
- Technology
- Energy Storage System
- Total capacity
- 100 MW
- Change in this agreement
- +100 MW
- Capacity effective from
- 27 April 2029
- Connection site
- Kilwinning 132/33kV
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Consents Approved
- Connections reform gate
- Gate 2
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Kilwinning 132/33kV
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem