πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

Grid infrastructure β€Ί Connection queue β€Ί Battery storage

BATTERY STORAGE Β· NGET

Warley

Warley is a 57 MW battery storage project consented, connecting to the National Grid (England & Wales) network at Warley 275kV Substation, with capacity due from October 2028. The connection agreement is held by Warley Battery Storage Limited.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2028 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-001113
Customer
Warley Battery Storage Limited
Technology
Energy Storage System
Total capacity
57 MW
Change in this agreement
+57 MW
Capacity effective from
30 October 2028
Connection site
Warley 275kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Consents Approved
Connections reform gate
Gate 2

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Warley Β· Grid map

Other projects at Warley 275kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem