Grid infrastructure βΊ Connection queue βΊ Battery storage
BATTERY STORAGE Β· NGETCodham Hall BESS
Codham Hall BESS is a 249 MW battery storage project in planning, connecting to the National Grid (England & Wales) network at Warley 275kV Substation, with capacity due from October 2037. The connection agreement is held by Pulse Clean Energy Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2037 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-003972
- Customer
- Pulse Clean Energy Limited
- Technology
- Energy Storage System
- Total capacity
- 249 MW
- Change in this agreement
- +249 MW
- Capacity effective from
- 31 October 2037
- Connection site
- Warley 275kV Substation
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Warley 275kV Substation
- Lebanon Farm 2 BESSBattery storage Β· 275 MW Β· Scoping
- Warley PV & BESSBattery storage Β· 250 MW Β· Scoping
- Blanketβs FarmBattery storage Β· 200 MW Β· Scoping
- Warley Battery Energy StorageBattery storage Β· 200 MW Β· Scoping
- WarleyBattery storage Β· 57 MW Β· Consents Approved
- Warley (tertiary)Solar + storage Β· 57 MW Β· Built
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem