Grid infrastructure β€Ί Connection queue β€Ί Onshore wind

ONSHORE WIND Β· SPT

Windy Standard III Wind Farm

Windy Standard III Wind Farm is a 88 MW onshore wind project consented, connecting to the SP Transmission (south Scotland) network at Dun Hill 132/33kV, with capacity due from October 2027. The connection agreement is held by Windy Standard III Limited.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2027 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-000359-2
Customer
Windy Standard III Limited
Technology
Wind Onshore
Total capacity
88 MW
Change in this agreement
+44 MW
Capacity effective from
31 October 2027
Connection site
Dun Hill 132/33kV
Transmission owner
SP Transmission (south Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Consents Approved
Connections reform gate
Gate 2

Connection site

The connection site could not be placed on the map.

Projects connecting near Dun Hill Β· Grid map

Other projects at Dun Hill 132/33kV

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem