🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

Home › Grid infrastructure › Connection queue

NESO TEC REGISTER · GREAT BRITAIN

Grid connection projects in the connection queue

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown2,255782.1 GW in total
In planning1,590scoping or awaiting consent
Consented or building265closest to connecting
Built400connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

2,255 projects · page 29 of 46
ProjectCapacityStageConnection siteFrom
Ourack Wind Farm
Wind + storage · Ourack Wind Farm LLP
105 MWScoping Ourack Wind Farm 132/33 kV Substation
SSEN Transmission (north Scotland)
Oct 2030
Glentarken Wind Farm
Onshore wind · SSE Renewables Services (UK) Limited
104 MWScoping Glentarken Wind Farm 132/33Kv Substation
SSEN Transmission (north Scotland)
Nov 2031
Beaw Field Wind Farm
Onshore wind · Beaw Field Shetland Limited
102 MWConsents Approved Beaw Field 132/33kV Substation
SSEN Transmission (north Scotland)
Oct 2032
Cockenzie BESS
Battery storage · Cockenzie Storage B Ltd
102 MWUnder Construction/Commissioning Meadowmill 400/132kV Substation
SP Transmission (south Scotland)
Jul 2027
Stranoch Wind Farm
Onshore wind · Stranoch Windfarm Limited
102 MWUnder Construction/Commissioning Stranoch Wind 132/33kV Substation
SP Transmission (south Scotland)
Apr 2027
Bhlaraidh Extension Wind Farm
Onshore wind · Sse Generation Limited
101 MWScoping Bhlaraidh 132/33kV Substation
SSEN Transmission (north Scotland)
Aug 2029
Cruach Bhreac Wind Farm
Onshore wind · Statkraft UK Ltd
101 MWScoping Craig Murrail 275kV Substation
SSEN Transmission (north Scotland)
Oct 2034
Dunach Wind Farm
Onshore wind · Galileo 04 Limited
101 MWScoping Dunach Wind 132Kv Substation
SSEN Transmission (north Scotland)
Oct 2034
Statkraft SEWF
Onshore wind · Statkraft UK Ltd
101 MWScoping Orrin GSP
SSEN Transmission (north Scotland)
Oct 2033
Alverdiscott
Battery storage · Pivoted Power LLP
100 MWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Oct 2036
Andrew BESS
Battery storage · Apatura Battery Ltd
100 MWScoping Andrew BESS 132kV Substation
SP Transmission (south Scotland)
Jul 2030
Bargatton Farm BESS
Battery storage · Lightsource Renewable UK Development Limited
100 MWScoping Bargatton Farm BESS 132kV Substation
SP Transmission (south Scotland)
Oct 2036
Bearsden BESS
Battery storage · Bearsden BESS Ltd
100 MWScoping Bearsden BESS 275Kv Substation
SP Transmission (south Scotland)
Oct 2029
Beauly 02 BESS
Battery storage · Field Beauly Ltd
100 MWScoping BEAULY 02 BESS 132kV SUBSTATION
SSEN Transmission (north Scotland)
Dec 2028
Berwick Solar Wind and Battery Storage
Solar + storage · Berwick Renewables Tx Limited
100 MWScoping Berwick 132/33kV
SP Transmission (south Scotland)
Oct 2031
Bradford West 100MW
Battery storage · Old Allen Road BESS Limited
100 MWConsents Approved Bradford West 275kV Substation
National Grid (England & Wales)
May 2027
Braidfield Battery Storage
Battery storage · Braidfield Battery Storage Limited
100 MWScoping Braidfield Battery Storage 132kV Substation
SP Transmission (south Scotland)
Sep 2027
Capenhurst 275KV Substation
Battery storage · Zenobe Capenhurst Limited
100 MWBuilt Capenhurst 275kV Substation
National Grid (England & Wales)
Cott's Farm
Solar + storage · Boralex Limited
100 MWScoping Cott's Farm 132kV Substation
SSEN Transmission (north Scotland)
Oct 2034
Didcot A GTs
Gas · RWE Generation UK Plc
100 MWBuilt Didcot 400kV Substation
National Grid (England & Wales)
Didcot Battery
Battery storage · Didcot Battery Limited
100 MWScoping Didcot 400/132Kv Substation
National Grid (England & Wales)
Mar 2027
Drongan Battery Storage
Battery storage · Drongan Battery Storage Ltd
100 MWScoping Coylton 275/132kV
SP Transmission (south Scotland)
Oct 2027
Dunside Wind Farm (Formally Fallago Rig 2 Wind Farm)
Onshore wind · Edf Energy Renewables Limited
100 MWAwaiting Consents Fallago 400/33kV
SP Transmission (south Scotland)
Apr 2029
EcoKilwinning
Solar + storage · Econergy International Limited
100 MWScoping Ecokilwinning 132Kv Substation
SP Transmission (south Scotland)
Oct 2031
Farm 100MW BESS
Battery storage · Apatura Battery Ltd
100 MWScoping Thurso South 275kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Feckenham 100MW BESS
Battery storage · Energycog Ltd
100 MWScoping Warwickshire Connection Node B 132kV Substation
National Grid (England & Wales)
Oct 2037
Fife Energy Centre
Battery storage · Cambridge Power Limited
100 MWScoping Fife Energy Centre 132kV substation
SP Transmission (south Scotland)
Oct 2028
Flemyland Battery Storage
Battery storage · Flemyland Battery Storage Limited
100 MWConsents Approved Kilwinning 132/33kV
SP Transmission (south Scotland)
Apr 2029
Frodsham Solar Park
Solar + storage · Frodsham Solar Limited
100 MWScoping Frodsham 132kV
National Grid (England & Wales)
Apr 2029
Fryston Lane 100MW BESS
Battery storage · GPC 2008 Ltd
100 MWScoping Leeds North Connection Node C 132kV Substation
National Grid (England & Wales)
Oct 2035
Galileo 08 Limited
Solar + storage · Galileo 08 Limited
100 MWScoping Mid Wales Connection Node A
National Grid (England & Wales)
Oct 2037
Hall Ings Farm Substation
Solar · O&G Group Limited
100 MWScoping Creyke Beck 132kV
National Grid (England & Wales)
Oct 2034
Kirkcaldy BESS
Battery storage · Apatura Battery Ltd
100 MWScoping Kirkcaldy BESS 132kV Substation
SP Transmission (south Scotland)
Oct 2032
Lairdmannoch Energy Park
Solar + storage · Lairdmannoch Energy Park Limited
100 MWAwaiting Consents Lairdmannoch Energy Park 132kV substation
SP Transmission (south Scotland)
Jun 2030
Larks Green Farm BESS
Battery storage · Voltalia UK Ltd
100 MWScoping Iron Acton 132kV Substation
National Grid (England & Wales)
Oct 2037
Learielaw Energy Storage
Battery storage · Learielaw Energy Storage Limited
100 MWScoping Learlielaw Energy Storage 132kV Substation
SP Transmission (south Scotland)
Oct 2028
Llyn Lort II Energy Park
Onshore wind · Llyn Lort II Energy Park Limited
100 MWScoping Chirk 132kV
National Grid (England & Wales)
Nov 2037
Menter Mon Morlais Anglesey Marine Energy
Other · Menter Môn Morlais Limited
100 MWUnder Construction/Commissioning Penrhos GSP
National Grid (England & Wales)
Mar 2030
Mossmorran Storage BESS
Battery storage · Rufusia Ltd
100 MWScoping Mossmorran Storage BESS 132KV Substation
SP Transmission (south Scotland)
Oct 2031
Mynydd Y Gwynt
Wind + storage · Edf Energy Renewables Limited
100 MWScoping Mid Wales Connection Node A 400Kv Substation
National Grid (England & Wales)
Oct 2037
Orchard BESS
Battery storage · RE Projects Development Limited
100 MWScoping Staffordshire Connection Node B 132kV Substation
National Grid (England & Wales)
Oct 2037
Pentland Floating Offshore Wind Farm
Offshore wind · Highland Wind Limited
100 MWConsents Approved Pentland Floating Offshore Wind Farm 132/66kV substation
SSEN Transmission (north Scotland)
Apr 2028
Saltcoats NEP BESS Facility
Battery storage · Rashley New Energy Limited
100 MWAwaiting Consents Saltcoats 132/33kV
SP Transmission (south Scotland)
Oct 2029
Sand Quarry Old Glasgow Road BESS
Battery storage · GPC 1134 Ltd
100 MWScoping Giffordland 400/132kV
SP Transmission (south Scotland)
May 2029
Scaraben Offshore Wind Farm
Offshore wind · Scaraben Offshore Wind Farm Limited
100 MWScoping Longside 132kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Sheilhill Battery Storage
Battery storage · Sheilhill Battery Storage Limited
100 MWAwaiting Consents St Fergus 132Kv Switching Station
SSEN Transmission (north Scotland)
Oct 2033
Sinclair Offshore Wind Farm
Offshore wind · Sinclair Offshore Wind Farm Limited
100 MWScoping Longside 132kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Sleat Hybrid
Wind + storage · Galileo 13 Limited
100 MWScoping Broadford GSP
SSEN Transmission (north Scotland)
Oct 2034
St Fergus
Solar + storage · Ib Vogt UK Ltd
100 MWScoping St Fergus
SSEN Transmission (north Scotland)
Oct 2033
Stretchford Farm Solar and Storage
Solar + storage · Bsr Applications Limited
100 MWScoping Abham 132kV Substation
National Grid (England & Wales)
Oct 2037
Page 29 of 46

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.