Grid infrastructure β€Ί Connection queue β€Ί Onshore wind

ONSHORE WIND Β· NGET

Llyn Lort II Energy Park

Llyn Lort II Energy Park is a 100 MW onshore wind project in planning, connecting to the National Grid (England & Wales) network at Chirk 132kV, with capacity due from November 2037. The connection agreement is held by Llyn Lort II Energy Park Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Nov 2037 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-002697
Customer
Llyn Lort II Energy Park Limited
Technology
Wind Onshore
Total capacity
100 MW
Change in this agreement
+100 MW
Capacity effective from
1 November 2037
Connection site
Chirk 132kV
Transmission owner
National Grid (England & Wales)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Scoping

Connection site

The connection site could not be placed on the map.

Projects connecting near Chirk Β· Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem