Demand (data centres, industry) projects in the connection queue

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown13.9 GW in total
In planning1scoping or awaiting consent
Consented or building0closest to connecting
Built0connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

1 projects
ProjectCapacityStageConnection siteFrom
Drax BECCS
Demand (data centres, industry) Β· Drax Power Limited
3.9 GWScoping Drax 400kV Substation
National Grid (England & Wales)
Oct 2035

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed β€œconnection nodes” are listed but not mapped.