Grid infrastructure β€Ί Connection queue β€Ί Onshore wind

ONSHORE WIND Β· SHET

Statkraft SEWF

Statkraft SEWF is a 101 MW onshore wind project in planning, connecting to the SSEN Transmission (north Scotland) network at Orrin GSP, with capacity due from October 2033. The connection agreement is held by Statkraft UK Ltd.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2033 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004828
Customer
Statkraft UK Ltd
Technology
Wind Onshore
Total capacity
101 MW
Change in this agreement
+101 MW
Capacity effective from
31 October 2033
Connection site
Orrin GSP
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Orrin GSP Β· Grid map

Other projects at Orrin GSP

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem